Sherbourne House

Project Summary

Strip out (almost to shell) of 6 floor office, including rooftop plant

Hospital.png

Commercial

Schedule of Work

Strip out of partitions, ceiling & floor finishes, kitchen/canteen facilities & WC's
Strip out of M&E from multiple floors including data services
Removal of air conditioning plant (interior plant rooms & roof top units)
Demolition of interior staircase & exterior canopy sections
Removal of revolving door & roller shutter doors

Project Gallery

Project Stats

Blank.png
Blank.png
Blank.png
sq. ft

97,000

14 Weeks

Services

Strip Out
M&E Strip Out
Int. & Ext. Demolition

Duration
Blank.png

Coventry

Location
Blank.png

Dean Marshall

Site Manager
Jack Kennedy