top of page

Sherbourne House
Project Summary
Strip out (almost to shell) of 6 floor office, including rooftop plant

Commercial
Schedule of Work
Strip out of partitions, ceiling & floor finishes, kitchen/canteen facilities & WC's
Strip out of M&E from multiple floors including data services
Removal of air conditioning plant (interior plant rooms & roof top units)
Demolition of interior staircase & exterior canopy sections
Removal of revolving door & roller shutter doors
Project Gallery
Project Stats



sq. ft
97,000
14 Weeks
Services
Strip Out
M&E Strip Out
Int. & Ext. Demolition
Duration

Coventry
Location

Dean Marshall
Site Manager

Map of case studies (click to see links)
bottom of page