SCC Data Centre & Offices
Project Summary
Combined strip out and groundworks project at large data centre & offices

Industrial
Schedule of Work
Customer
Strip Out:
Strip out floor finishes, raised floors & suspended ceilings
Remove HVAC system, radiators, sanitaryware
Remove electrical & data services equipment & cabling
Remove & disposed of wall finishes inc. tiles
Demolish covered walkway, curtain walling & block walls
Remove fixtures & fittings inc. windows, doors, panels, frames, glazing
Groundworks:
Excavation & filling with earthwork supports
Preparations for installation of storm drainage
Landscaping; clearance of vegetation & excavation
Installation of fencing
Concrete slab foundations
Speller Metcalfe
Project Stats



Project Value
£470,000
20 Weeks
Services
Soft Strip Out
Internal Demolition
M&E Strip Out
Groundworks
Duration

Birmingham
Location

John Treacy
Site Manager
