Project Summary

Major strip out & internal demolition in prestigious University buildings

Hospital.png

Education

Schedule of Work

Strip out floor finishes, raised floors & suspended ceilings
Demolish non-load bearing walls & remove partitions
Remove lift car
Remove HVAC system, ducting & pipework, radiators & associated roof level plant
Strip out WC's & sanitaryware
Remove electrical & data services equipment & cabling

Project Gallery

Project Stats

Blank.png
Blank.png
Blank.png
sq. ft

41,000

15 Weeks

Services

Soft Strip Out
Internal Demolition
M&E Strip Out

Duration
Blank.png

Birmingham

Location
Blank.png

Simon Pettitt

Contracts Manager
Jack Kennedy

Map of case studies (click to see links)