Project Summary

Soft strip out of former NHS offices prior to Category 'A' refurbishment for Aston University

Hospital.png

Education

Schedule of Work

Remove floor surfaces
Strip out partition walls
Remove electrical & data services equipment & cabling
Remove of kitchen & 3 roller-racking systems

Project Gallery

Project Stats

Blank.png
Blank.png
Blank.png
Approx. Value

<£10,000

1 Week

Services

Soft Strip Out
Internal Demolition
M&E Strip Out