Nationwide Training Facility

Project Summary

Dismantling and demolition of a Nationwide Building Society training facility; a branch mock-up located within Newcombe House

Hospital.png

Retail

Schedule of Work

Remove partition walls, glazed partitions & wall linings
Demolish & remove blockwork structures & 15m dividing wall
Remove fixtures & fittings, floor finishes & raised floor
Remove ceilings & light fittings
Remove M&E; power & data installations & cabling, fire alarm, inc. detectors and CCTV system
Disconnect & remove roller shutter

Project Gallery

Project Stats

Blank.png
Blank.png
Blank.png
sq. ft

4,950

2.5 Weeks

Services

Soft Strip Out
Internal Demolition

Duration
Blank.png

Swindon

Location
Blank.png

John Treacy

Site Manager
Jack Kennedy

Map of case studies (click to see links)