Nationwide Training Facility
Project Summary
Dismantling and demolition of a Nationwide Building Society training facility; a branch mock-up located within Newcombe House

Retail
Schedule of Work
Customer
Remove partition walls, glazed partitions & wall linings
Demolish & remove blockwork structures & 15m dividing wall
Remove fixtures & fittings, floor finishes & raised floor
Remove ceilings & light fittings
Remove M&E; power & data installations & cabling, fire alarm, inc. detectors and CCTV system
Disconnect & remove roller shutter
Barnwood
Project Stats



sq. ft
4,950
2.5 Weeks
Services
Soft Strip Out
Internal Demolition
Duration

Swindon
Location

John Treacy
Site Manager