Strip out of 5th floor offices & comms room in SE1

Hospital.png

Commercial

Schedule of Work

Strip out stud wall & glazed partitions & doors
Remove suspended ceilings & carpeted floor finish
Strip out plasterboard ceilings and column casings
Strip out comms room, kitchenette, WCs, radiators & shower
Strip out raised floor cut outs & below floor data cables

Project Gallery

Project Stats

Blank.png
Blank.png
Blank.png
sq. ft

6,500

3.5 weeks