Headlam
Project Summary
Office strip out & removal of small mezzanine within warehouse

Commercial
Schedule of Work
Remove plasterboard stud partition walls
Strip out ceiling & floor finishes
Strip out kitchen & WC's
Dismantle & remove mezzanine and make good slab base
Project Gallery
Project Stats



sq. ft
7,200
2 Weeks
Services
Soft Strip Out
Internal Demolition
Duration

Swindon
Location

Chris Santini
Site Manager