Great Charles Street

Project Summary

Strip out of offices and removal of major plant

Hospital.png

Commercial

Schedule of Work

Strip out floor finishes & suspended ceilings from multiple floors
Demolish non-load bearing walls & partitions
Removed air conditioning plant (two interior plant rooms & roof top)
A gantry was custom-built to facilitate plant removal from the roof top
Remove and recycle all debris & waste materials

Project Gallery

Project Stats

Blank.png
Blank.png
Blank.png
sq. ft

21,500

2 Weeks

Services

Soft Strip Out
Internal Demolition
M&E Strip Out

Duration
Blank.png

Birmingham

Location
Blank.png