Dr Martens, Camden
Project Summary
Soft strip out of former 'Dr Martens' offices , including removal of metallic ceiling tiles

Retail
Schedule of Work
Strip out suspended ceiling tiles & grid
Strip out timber decking and seating
Remove partitions & bar area
Strip out tea points
Project Gallery
Project Stats



sq. ft
5,575
1.5 Weeks
Services
Soft Strip Out
Duration

Camden, London
Location

Jack Morton
Contracts Manager