Strip out of multiple theatres and foyer at multiplex cinema

Hospital.png

Hospitality & Leisure

Schedule of Work

Strip out foyer including ticket counters & concession store
Remove theatre seating
Strip out WC's and sanitary ware
Remove floor finishes & wall finishes
Strip out suspended ceilings and grid
Demolish partition walls and glazed curtain walling & doors
Remove spiral staircases
Remove and recycle all debris & waste materials

Project Stats

Blank.png
Blank.png
Blank.png
sq. ft

53,000

2 Weeks