top of page

Caxton Gate

Project Summary

Internal demolition prior to major structural remodelling at city centre retail outlet

Hospital.png

Retail

Schedule of Work

Remove previous tenant's furniture, fixtures & fittings
Remove staircases & enclosures
Remove lift & lift shaft
Remove concrete floor slab
Remove full-height walls, ramps
Dismantle & remove HVAC systems & ducting, electrical services & data services
Remove and recycle all debris & waste materials

Project Gallery

Project Stats

Blank.png
Blank.png
Blank.png
sq. ft

9,700

8 Weeks

Services

Soft Strip Out
Internal Demolition
M&E Strip Out

Duration
Blank.png

Birmingham

Location
Blank.png

Ken Taylor

Site Manager
Jack Kennedy