Business School, UOB

Project Summary

Strip out and internal demolition of lecture theatre in University business school

Education

Schedule of Work

Customer

Remove lecture theatre seating & screens
Strip out staging and seat tiering
Remove Floor finishes & suspended ceilings
Remove decorative wall finishes
Remove and recycle all debris & waste materials

GTH

Project Stats

Project Value

£11,000

1.5 Weeks

Services

Soft Strip Out
Internal Demolition

Duration

Birmingham

Location

Dean Marshall

Site Manager

Project Gallery

PUNCTUAL

Stephen Pallett, Contracts Manager

“Umberslade are always punctual, polite to the client and our staff and their work is clean & tidy. Overall they do a great job in demanding situations.”