Bank House

Project Summary

Dismantling and demolition of glazed curtain walling around internal courtyard (to increase office space)

Commercial

Schedule of Work

Customer

Remove glazed curtain walling & installation of structural support
Demolition of block walls
Remove multi-layer roof surfaces
Remove and recycle all debris & waste materials

Intex Projects

Project Stats

Project Value

£20,000

3 Weeks

Services

Internal Demolition

Duration

Milton Keynes

Location

Ken Taylor

Site Manager

Project Gallery

PUNCTUAL

Stephen Pallett, Contracts Manager

“Umberslade are always punctual, polite to the client and our staff and their work is clean & tidy. Overall they do a great job in demanding situations.”