CASE STUDY : LARGE RETAIL STRIP OUT

Project

Strip out of three adjacent retail units at major retail park

Location

The Fort Retail Park, Birmingham

Services

Strip Out / Internal Demolition

Duration

3 Weeks

Main Contractor

Lawfield Contracts Ltd.

Value of Project

£70,000

Work Carried Out
  • Demolish dividing walls between units

  • Strip out offices and staff room

  • Strip out stock rooms and remove racking

  • Remove ceiling systems and floor coverings

  • Demolish changing areas

“Excellent job by the Umberslade team, we won’t hesitate to use their services again.”

 

S Field, Lawfield Contracts

Before & After Comparison
Time lapse video: retail units strip out
 

PUNCTUAL

Stephen Pallett, Contracts Manager

“Umberslade are always punctual, polite to the client and our staff and their work is clean & tidy. Overall they do a great job in demanding situations.”