1/9

CASE STUDY : UNIVERSITY STRIP OUT

Project

Demolition and strip out of two major lecture theatres

Location

University of Derby

Services

Strip Out / Internal Demolition

Duration

4 weeks

Main Contractor

Domino Commercial Interiors

Value of Project

£33,000

Work Carried Out
  • Removed lecture theatre seating

  • Demolished staging and seat tiering

  • Floor & ceiling tile removal

  • Removed decorative wall finishes

  • Removed air conditioning plant and ducting

  • Removed doors, frames, floor-fixed balustrade and handrails

PUNCTUAL

Stephen Pallett, Contracts Manager

“Umberslade are always punctual, polite to the client and our staff and their work is clean & tidy. Overall they do a great job in demanding situations.”

  • LinkedIn
  • Twitter
  • Facebook
  • YouTube

© 2021 Umberslade Business Services Ltd.

Umberslade White 300dpi_capabilities_log