CASE STUDY : COMBINED STRIP OUT & GROUNDWORKS

Project

Our strip out & groundworks teams work together to prepare a school of historical interest for a major refurbishment

Location

Osborne Primary School, Erdington

Services

Strip Out & Groundworks

 

Duration

Phased over 12 Months

Main Contractor

Value of Project

£850,000

Work Carried Out : Strip Out
  • Removal of lathe & plaster ceilings & stud partition walls

  • Removal of doors & frames, windows & window boards, parquet flooring, vinyl flooring & carpets, skirting boards, dado rails, picture rails, curtains, blinds & pelmets

  • Removal of kitchen, sanitary ware and M&E installations

Work Carried Out : Groundworks
  • Drainage work, installation of attenuation tank

  • Internal floor slab replacement in two buildings

  • Underpinning of main building

  • Built in-situ concerete stairs to basement

  • Concrete raft foundations

  • Formation of structural openings

Time Lapse Video: Floor Removal & Concrete Pour
Time Lapse Video: Pouring 130m2 Raft Slab
 

PUNCTUAL

Stephen Pallett, Contracts Manager

Umberslade are always punctual, polite to the client and our staff and their work is clean & tidy. Overall they do a great job in demanding situations.

 